Westfield Stratford nears completion

Jasper Hijink • Oct 29, 2021


Months of work brings the end near for Westfield Stratford - phase I

Years of preparation, months of co-ordination and weeks of commissioning, but we are getting close to complete this phase of Westfield Stratford Shopping Centre.


In phase I all the back-of-house lighting was changed from (in general) conventional 58W fluorescents to 25W LED luminaires. Each light had a sensor and a Mymesh module on board to create a large wireless mesh network. Based on presence detection lamps dim and switch to deliver maximum energy saving to the client. Furthermore, all emergency lighting is tested and monitored for compliance.


The last couple of days commissioning are planned in, and the dashboard is being worked on in the back office. Exciting to see it all come together in the next couple of weeks.

SHARE

by Connor Felstead 07 Oct, 2024
St Thomas’ Hospital expands with The Core
by Connor Felstead 16 Sept, 2024
Gravesend upgrades the lighting in Cascades
by Jasper Hijink 12 Sept, 2024
Unipart - NHS Supply Chain warehouse
by Connor Felstead 12 Sept, 2024
Bluewater uses Mymesh to upgrade the Toilet areas to Smart
by Jasper Hijink 11 Sept, 2024
Norwich Community Hospital's new £19.2m wing
by Jasper Hijink 10 Sept, 2024
Mymesh successfully extends the IASME IoT Cyber Assurance Certification (Level 2)
by Craig Stead 06 Sept, 2024
Circular Lighting Live
by Nicola Osborne 06 Sept, 2024
Exciting News...
by Ray Molony 05 Sept, 2024
St Thomas’ Hospital reuses lights and adds intelligence in major upgrade
MORE POSTS
Share by: